How long does a Commercial / Multi Family Project permit take in Ricardo Ranch, Calgary?

Rolling 24 months · Sample: 32
Median days · Applied → Issued
27 days
Sample: 32 permits, last 24 months
Median days · Issued → Completed
207 days
From permit issuance to completion
City-wide median
42 days
Ricardo Ranch is 15 days faster

Recent examples in Ricardo Ranch

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-17223Unspecified2026-09-092026-09-112$50K
BP2026-11564New2026-06-232026-08-1149$1.5M
BP2026-13302NewJayman Built2026-07-162026-08-0520$1.7M
BP2026-13297NewJayman Built2026-07-162026-08-0419$2.2M
BP2026-13213New2026-07-152026-08-0420$1.5M