How long does a Commercial / Multi Family Project permit take in Residual Ward 2 Sub Area 2f, Calgary?

Rolling 24 months · Sample: 13
Median days · Applied → Issued
27 days
Sample: 13 permits, last 24 months
Median days · Issued → Completed
89 days
From permit issuance to completion
City-wide median
42 days
Residual Ward 2 Sub Area 2f is 15 days faster

Recent examples in Residual Ward 2 Sub Area 2f

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-04743Improvement2026-03-262026-05-2055$180K
BP2026-02825ImprovementCidex Development2026-02-252026-03-1013$17K
BP2025-18438Improvement2025-09-192025-11-0547$70K
BP2025-15190Improvement2025-08-062025-10-1671$50K
BP2025-13208Improvement2025-07-082025-08-1134$130K