How long does a Commercial / Multi Family Project permit take in Residual Ward 2 Sub Area 2e, Calgary?
Median days · Applied → Issued
26 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
251 days
From permit issuance to completion
City-wide median
42 days
Residual Ward 2 Sub Area 2e is 16 days faster
Recent examples in Residual Ward 2 Sub Area 2e
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14829 | Improvement | — | 2026-08-06 | 2026-08-31 | 25 | $245K |
| BP2025-18709 | Improvement | Lignum Interiors | 2025-09-23 | 2025-10-09 | 16 | $180K |
| BP2025-14268 | Improvement | Westcor Construction | 2025-07-23 | 2025-09-29 | 68 | $3.6M |
| BP2025-11809 | Improvement | Bosch Building Technologies | 2025-06-19 | 2025-07-23 | 34 | $500K |
| BP2025-05817 | Unspecified | — | 2025-04-03 | 2025-04-30 | 27 | $2K |