How long does a Commercial / Multi Family Project permit take in Residual Ward 2 Sub Area 2c, Calgary?

Rolling 24 months · Sample: 24
Median days · Applied → Issued
51 days
Sample: 24 permits, last 24 months
Median days · Issued → Completed
275 days
From permit issuance to completion
City-wide median
42 days
Residual Ward 2 Sub Area 2c is 9 days slower

Recent examples in Residual Ward 2 Sub Area 2c

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14031ImprovementPrimeridge Construction2026-07-272026-08-2529$75K
BP2026-13497Improvement2026-07-202026-08-1223$155K
BP2026-09276Improvement2026-05-272026-07-2963$25K
BP2026-09941Improvement2026-06-022026-07-0634$220K
BP2026-04738Improvement2026-03-262026-06-0167$101K