How long does a Residential Improvement Project permit take in Residual Ward 12 Sub Area 12b, Calgary?
Median days · Applied → Issued
43 days
Sample: 3 permits, last 24 months
Median days · Issued → Completed
221 days
From permit issuance to completion
City-wide median
17 days
Residual Ward 12 Sub Area 12b is 26 days slower
Recent examples in Residual Ward 12 Sub Area 12b
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2025-22095 | Improvement | Kay 2 Contracting | 2025-11-14 | 2026-01-15 | 62 | $50K |
| BP2025-17179 | New | — | 2025-09-03 | 2025-10-16 | 43 | $198K |
| BP2025-12081 | Improvement | — | 2025-06-23 | 2025-07-30 | 37 | $15K |