How long does a Commercial / Multi Family Project permit take in Residual Ward 12 Sub Area 12a, Calgary?
Median days · Applied → Issued
104 days
Sample: 18 permits, last 24 months
Median days · Issued → Completed
170 days
From permit issuance to completion
City-wide median
42 days
Residual Ward 12 Sub Area 12a is 62 days slower
Recent examples in Residual Ward 12 Sub Area 12a
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14157 | Improvement | — | 2026-07-27 | 2026-08-13 | 17 | $6K |
| BP2026-02058 | Unspecified | — | 2026-02-11 | 2026-08-11 | 181 | $200K |
| BP2026-05173 | Improvement | Scott Builders | 2026-04-02 | 2026-07-07 | 96 | $350K |
| BP2026-08192 | Unspecified | Johnson Controls Canada | 2026-05-12 | 2026-05-14 | 2 | $100K |
| BP2025-16636 | Unspecified | Azimuth Builders | 2025-08-26 | 2026-04-30 | 247 | $240K |