How long does a Commercial / Multi Family Project permit take in Residual Ward 1 Sub Area 1b, Calgary?
Median days · Applied → Issued
26 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
28 days
From permit issuance to completion
City-wide median
42 days
Residual Ward 1 Sub Area 1b is 16 days faster
Recent examples in Residual Ward 1 Sub Area 1b
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13240 | Unspecified | — | 2026-07-15 | 2026-07-24 | 9 | $112 |
| BP2026-05691 | Unspecified | — | 2026-04-10 | 2026-05-06 | 26 | $50K |
| BP2025-08644 | Unspecified | — | 2025-05-09 | 2025-06-09 | 31 | $0 |
| BP2025-09025 | Unspecified | — | 2025-05-14 | 2025-05-21 | 7 | $45K |
| BP2024-17058 | Improvement | Balzers Canada | 2024-08-15 | 2024-11-19 | 96 | $742K |