How long does a Commercial / Multi Family Project permit take in Renfrew, Calgary?

Rolling 24 months · Sample: 58
Median days · Applied → Issued
63 days
Sample: 58 permits, last 24 months
Median days · Issued → Completed
249 days
From permit issuance to completion
City-wide median
42 days
Renfrew is 21 days slower

Recent examples in Renfrew

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-10688NewZ Group2026-06-112026-08-2777$338K
BP2026-16160ImprovementRescon Concrete Restorations2026-08-252026-08-261$65K
BP2026-09877ImprovementKamex Construction2026-06-022026-08-1877$135K
BP2025-21479NewOldstreet Development2025-11-042026-07-27265$1.6M
BP2025-21494NewOldstreet Development2025-11-042026-07-27265$1.3M