How long does a Commercial / Multi Family Project permit take in Red Carpet, Calgary?
Median days · Applied → Issued
160 days
Sample: 14 permits, last 24 months
Median days · Issued → Completed
251 days
From permit issuance to completion
City-wide median
42 days
Red Carpet is 118 days slower
Recent examples in Red Carpet
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2025-11432 | New | Kalamoir Construction | 2025-06-13 | 2026-05-14 | 335 | $19.3M |
| BP2025-11480 | New | Kalamoir Construction | 2025-06-16 | 2025-12-18 | 185 | $8.9M |
| BP2025-04446 | New | Kalamoir Construction | 2025-03-17 | 2025-07-08 | 113 | $1.1M |
| BP2025-04445 | New | Kalamoir Construction | 2025-03-17 | 2025-06-16 | 91 | $825K |
| BP2024-19517 | New | Kalamoir Construction | 2024-09-13 | 2025-03-06 | 174 | $1.7M |