How long does a Residential Improvement Project permit take in Queensland, Calgary?
Median days · Applied → Issued
19 days
Sample: 71 permits, last 24 months
Median days · Issued → Completed
98 days
From permit issuance to completion
City-wide median
17 days
Queensland is 2 days slower
Recent examples in Queensland
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16481 | New | Starytec | 2026-08-28 | 2026-09-10 | 13 | $60K |
| BP2026-15078 | New | — | 2026-08-10 | 2026-09-02 | 23 | $80K |
| BP2026-14004 | New | Toy Box Garage | 2026-07-26 | 2026-08-17 | 22 | $56K |
| BP2026-12620 | Improvement | Canwest Concrete Cutting and Coring | 2026-07-07 | 2026-07-30 | 23 | $3K |
| BP2026-07804 | New | Ht Ranch Contracting | 2026-05-07 | 2026-07-16 | 70 | $39K |