How long does a Residential Improvement Project permit take in Pump Hill, Calgary?
Median days · Applied → Issued
17 days
Sample: 21 permits, last 24 months
Median days · Issued → Completed
225 days
From permit issuance to completion
City-wide median
17 days
Same as Pump Hill
Recent examples in Pump Hill
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15366 | Improvement | Solid Solutions | 2026-08-13 | 2026-08-31 | 18 | $300K |
| BP2026-07164 | Improvement | — | 2026-04-29 | 2026-06-05 | 37 | $250K |
| BP2026-02998 | Improvement | Hl Contracting | 2026-02-26 | 2026-04-08 | 41 | $38K |
| BP2026-01877 | Improvement | Shift Accessibility Contractors | 2026-02-07 | 2026-03-10 | 31 | $150K |
| BP2026-00212 | Improvement | Diamond Fireplace Distributors | 2026-01-07 | 2026-01-16 | 9 | $2K |