How long does a Commercial / Multi Family Project permit take in Parkhill, Calgary?
Median days · Applied → Issued
71 days
Sample: 11 permits, last 24 months
Median days · Issued → Completed
140 days
From permit issuance to completion
City-wide median
42 days
Parkhill is 29 days slower
Recent examples in Parkhill
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2025-21080 | New | Trustpro Development | 2025-10-28 | 2026-02-04 | 99 | $859K |
| BP2025-20616 | New | Baidwan Construction | 2025-10-21 | 2026-01-26 | 97 | $1.4M |
| BP2026-00150 | Unspecified | — | 2026-01-06 | 2026-01-07 | 1 | $12K |
| BP2025-20443 | Improvement | — | 2025-10-20 | 2025-12-30 | 71 | $65K |
| BP2025-23432 | Unspecified | — | 2025-12-09 | 2025-12-10 | 1 | $4K |