How long does a Commercial / Multi Family Project permit take in Palliser, Calgary?
Median days · Applied → Issued
19 days
Sample: 11 permits, last 24 months
Median days · Issued → Completed
103 days
From permit issuance to completion
City-wide median
42 days
Palliser is 23 days faster
Recent examples in Palliser
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10970 | Improvement | — | 2026-06-15 | 2026-08-11 | 57 | $55K |
| BP2026-10507 | Unspecified | — | 2026-06-09 | 2026-06-16 | 7 | $9K |
| BP2025-21621 | Improvement | — | 2025-11-06 | 2025-12-29 | 53 | $0 |
| BP2025-19472 | Improvement | — | 2025-10-03 | 2025-10-28 | 25 | $10K |
| BP2025-18245 | Improvement | Afcg Construction | 2025-09-17 | 2025-10-08 | 21 | $130K |