How long does a Commercial / Multi Family Project permit take in Nolan Hill, Calgary?
Median days · Applied → Issued
47 days
Sample: 18 permits, last 24 months
Median days · Issued → Completed
216 days
From permit issuance to completion
City-wide median
42 days
Nolan Hill is 5 days slower
Recent examples in Nolan Hill
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10418 | Improvement | A2z Building Solutions | 2026-06-09 | 2026-07-16 | 37 | $60K |
| BP2026-09634 | Improvement | Stealth Homes | 2026-05-29 | 2026-07-02 | 34 | $96K |
| BP2026-05302 | Improvement | — | 2026-04-06 | 2026-05-22 | 46 | $348K |
| BP2025-03522 | New | Cidex Development | 2025-02-28 | 2026-01-03 | 309 | $2.7M |
| BP2025-21743 | Improvement | — | 2025-11-07 | 2025-12-31 | 54 | $1K |