How long does a Residential Improvement Project permit take in Monterey Park, Calgary?
Median days · Applied → Issued
22 days
Sample: 62 permits, last 24 months
Median days · Issued → Completed
88 days
From permit issuance to completion
City-wide median
17 days
Monterey Park is 5 days slower
Recent examples in Monterey Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14346 | Improvement | Yenz Design | 2026-07-29 | 2026-09-08 | 41 | $74K |
| BP2026-11374 | New | Alta Home | 2026-06-20 | 2026-07-06 | 16 | $59K |
| BP2026-10625 | Improvement | — | 2026-06-10 | 2026-06-11 | 1 | $0 |
| BP2026-06496 | New | — | 2026-04-21 | 2026-05-08 | 17 | $51K |
| BP2026-04206 | Improvement | Westframe Consruction | 2026-03-19 | 2026-04-22 | 34 | $11K |