How long does a Commercial / Multi Family Project permit take in Millrise, Calgary?
Median days · Applied → Issued
31 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
82 days
From permit issuance to completion
City-wide median
42 days
Millrise is 11 days faster
Recent examples in Millrise
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10086 | New | Kamex Construction | 2026-06-04 | 2026-08-05 | 62 | $75K |
| BP2025-19579 | New | Kamex Construction | 2025-10-06 | 2025-12-16 | 71 | $95K |
| BP2025-12603 | Improvement | Okotoks Home Improvements | 2025-06-30 | 2025-07-21 | 21 | $20K |
| BP2025-01589 | Improvement | — | 2025-01-29 | 2025-02-24 | 26 | $10K |
| BP2025-00366 | Improvement | — | 2025-01-08 | 2025-02-05 | 28 | $15K |