How long does a Commercial / Multi Family Project permit take in Midnapore, Calgary?

Rolling 24 months · Sample: 43
Median days · Applied → Issued
28 days
Sample: 43 permits, last 24 months
Median days · Issued → Completed
145 days
From permit issuance to completion
City-wide median
42 days
Midnapore is 14 days faster

Recent examples in Midnapore

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13493Improvement2026-07-202026-08-0516$40K
BP2026-11993ImprovementRiad Contracting2026-06-292026-07-2930$80K
BP2026-09576Improvement2026-05-292026-06-2527$10K
BP2026-09218Improvement2026-05-262026-06-2227$1M
BP2026-03614Improvement2026-03-102026-04-2748$716K