How long does a Commercial / Multi Family Project permit take in Midnapore, Calgary?
Median days · Applied → Issued
28 days
Sample: 43 permits, last 24 months
Median days · Issued → Completed
145 days
From permit issuance to completion
City-wide median
42 days
Midnapore is 14 days faster
Recent examples in Midnapore
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13493 | Improvement | — | 2026-07-20 | 2026-08-05 | 16 | $40K |
| BP2026-11993 | Improvement | Riad Contracting | 2026-06-29 | 2026-07-29 | 30 | $80K |
| BP2026-09576 | Improvement | — | 2026-05-29 | 2026-06-25 | 27 | $10K |
| BP2026-09218 | Improvement | — | 2026-05-26 | 2026-06-22 | 27 | $1M |
| BP2026-03614 | Improvement | — | 2026-03-10 | 2026-04-27 | 48 | $716K |