How long does a Commercial / Multi Family Project permit take in Meridian, Calgary?

Rolling 24 months · Sample: 28
Median days · Applied → Issued
35 days
Sample: 28 permits, last 24 months
Median days · Issued → Completed
118 days
From permit issuance to completion
City-wide median
42 days
Meridian is 7 days faster

Recent examples in Meridian

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15119Improvement2026-08-102026-09-0324$811K
BP2026-10948ImprovementHaides Construction2026-06-152026-08-1157$300K
BP2026-12939ImprovementHaides Construction2026-07-112026-07-176$5K
BP2026-08992Improvement2026-05-222026-07-1655$75K
BP2026-09945Improvement2026-06-022026-07-0533$0