How long does a Commercial / Multi Family Project permit take in Meridian, Calgary?
Median days · Applied → Issued
35 days
Sample: 28 permits, last 24 months
Median days · Issued → Completed
118 days
From permit issuance to completion
City-wide median
42 days
Meridian is 7 days faster
Recent examples in Meridian
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15119 | Improvement | — | 2026-08-10 | 2026-09-03 | 24 | $811K |
| BP2026-10948 | Improvement | Haides Construction | 2026-06-15 | 2026-08-11 | 57 | $300K |
| BP2026-12939 | Improvement | Haides Construction | 2026-07-11 | 2026-07-17 | 6 | $5K |
| BP2026-08992 | Improvement | — | 2026-05-22 | 2026-07-16 | 55 | $75K |
| BP2026-09945 | Improvement | — | 2026-06-02 | 2026-07-05 | 33 | $0 |