How long does a Commercial / Multi Family Project permit take in Medicine Hill, Calgary?
Median days · Applied → Issued
60 days
Sample: 57 permits, last 24 months
Median days · Issued → Completed
195 days
From permit issuance to completion
City-wide median
42 days
Medicine Hill is 18 days slower
Recent examples in Medicine Hill
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-08528 | New | Eagle Builders | 2026-05-15 | 2026-08-06 | 83 | $13M |
| BP2026-08045 | Improvement | — | 2026-05-10 | 2026-07-15 | 66 | $25K |
| BP2026-09293 | Improvement | — | 2026-05-27 | 2026-06-24 | 28 | $85K |
| BP2026-06755 | Improvement | — | 2026-04-24 | 2026-06-16 | 53 | $126K |
| BP2026-05142 | Improvement | — | 2026-04-01 | 2026-05-29 | 58 | $100K |