How long does a Commercial / Multi Family Project permit take in Medicine Hill, Calgary?

Rolling 24 months · Sample: 57
Median days · Applied → Issued
60 days
Sample: 57 permits, last 24 months
Median days · Issued → Completed
195 days
From permit issuance to completion
City-wide median
42 days
Medicine Hill is 18 days slower

Recent examples in Medicine Hill

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-08528NewEagle Builders2026-05-152026-08-0683$13M
BP2026-08045Improvement2026-05-102026-07-1566$25K
BP2026-09293Improvement2026-05-272026-06-2428$85K
BP2026-06755Improvement2026-04-242026-06-1653$126K
BP2026-05142Improvement2026-04-012026-05-2958$100K