How long does a Commercial / Multi Family Project permit take in Meadowlark Park, Calgary?
Median days · Applied → Issued
36 days
Sample: 60 permits, last 24 months
Median days · Issued → Completed
127 days
From permit issuance to completion
City-wide median
42 days
Meadowlark Park is 6 days faster
Recent examples in Meadowlark Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15336 | Improvement | — | 2026-08-13 | 2026-09-03 | 21 | $750K |
| BP2026-14180 | Improvement | — | 2026-07-28 | 2026-08-24 | 27 | $1.2M |
| BP2026-14099 | Improvement | — | 2026-07-27 | 2026-08-22 | 26 | $10K |
| BP2026-13382 | Improvement | — | 2026-07-17 | 2026-08-14 | 28 | $80K |
| BP2026-11886 | Improvement | — | 2026-06-26 | 2026-07-22 | 26 | $50K |