How long does a Commercial / Multi Family Project permit take in McKenzie Lake, Calgary?
Median days · Applied → Issued
45 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
96 days
From permit issuance to completion
City-wide median
42 days
McKenzie Lake is 3 days slower
Recent examples in McKenzie Lake
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13096 | New | Kamex Construction | 2026-07-14 | 2026-08-20 | 37 | $150K |
| BP2026-07529 | New | Kamex Construction | 2026-05-04 | 2026-06-18 | 45 | $300K |
| BP2026-06795 | Improvement | Canwest Concrete Cutting and Coring | 2026-04-24 | 2026-06-05 | 42 | $10K |
| BP2026-01793 | Improvement | — | 2026-02-05 | 2026-03-31 | 54 | $100 |
| BP2025-14570 | Improvement | — | 2025-07-27 | 2026-01-15 | 172 | $500K |