How long does a Commercial / Multi Family Project permit take in Mayland, Calgary?

Rolling 24 months · Sample: 18
Median days · Applied → Issued
48 days
Sample: 18 permits, last 24 months
Median days · Issued → Completed
115 days
From permit issuance to completion
City-wide median
42 days
Mayland is 6 days slower

Recent examples in Mayland

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15971Unspecified2026-08-212026-09-1121$8K
BP2026-13712Improvement2026-07-222026-08-1322$50K
BP2026-10149ImprovementCougar Contractors2026-06-042026-07-3056$3.5M
BP2026-10113Improvement2026-06-042026-07-2955$40K
BP2026-10419ImprovementCalcon Construction2026-06-092026-07-0728$675K