How long does a Residential Improvement Project permit take in Mayfair, Calgary?
Median days · Applied → Issued
60 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
310 days
From permit issuance to completion
City-wide median
17 days
Mayfair is 43 days slower
Recent examples in Mayfair
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-07261 | Improvement | Monogram Homes | 2026-04-30 | 2026-08-12 | 104 | $450K |
| BP2025-16685 | Improvement | — | 2025-08-26 | 2026-01-26 | 153 | $173K |
| BP2025-16888 | Improvement | — | 2025-08-29 | 2025-11-27 | 90 | $76K |
| BP2025-12614 | New | — | 2025-06-30 | 2025-10-02 | 94 | $28K |
| BP2025-13785 | Improvement | — | 2025-07-16 | 2025-08-15 | 30 | $0 |