How long does a Single Construction Permit permit take in Maple Ridge, Calgary?
Median days · Applied → Issued
60 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
291 days
From permit issuance to completion
City-wide median
18 days
Maple Ridge is 42 days slower
Recent examples in Maple Ridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-05632 | New | National Star Homes | 2026-04-09 | 2026-06-08 | 60 | $142K |
| BP2026-05634 | New | National Star Homes | 2026-04-09 | 2026-06-08 | 60 | $142K |
| BP2025-22668 | New | Mimar Homes | 2025-11-25 | 2026-01-21 | 57 | $235K |
| BP2025-22671 | New | Mimar Homes | 2025-11-25 | 2026-01-21 | 57 | $198K |
| BP2024-26266 | New | Destiny Design and Build | 2024-12-20 | 2025-03-03 | 73 | $0 |