How long does a Commercial / Multi Family Project permit take in Manchester, Calgary?
Median days · Applied → Issued
60 days
Sample: 29 permits, last 24 months
Median days · Issued → Completed
128 days
From permit issuance to completion
City-wide median
42 days
Manchester is 18 days slower
Recent examples in Manchester
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10803 | Improvement | — | 2026-06-12 | 2026-09-11 | 91 | $550K |
| BP2026-12583 | Improvement | — | 2026-07-07 | 2026-09-10 | 65 | $150K |
| BP2026-11203 | Improvement | — | 2026-06-18 | 2026-08-25 | 68 | $20K |
| BP2026-14173 | Unspecified | — | 2026-07-28 | 2026-07-30 | 2 | $4K |
| BP2026-08706 | Improvement | — | 2026-05-19 | 2026-06-17 | 29 | $75K |