How long does a Commercial / Multi Family Project permit take in Lower Mount Royal, Calgary?
Median days · Applied → Issued
27 days
Sample: 37 permits, last 24 months
Median days · Issued → Completed
160 days
From permit issuance to completion
City-wide median
42 days
Lower Mount Royal is 15 days faster
Recent examples in Lower Mount Royal
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14920 | Improvement | Crystal Image Construction | 2026-08-07 | 2026-09-03 | 27 | $100K |
| BP2026-16179 | Unspecified | — | 2026-08-25 | 2026-08-26 | 1 | $100K |
| BP2026-15182 | Improvement | Proflex Contracting | 2026-08-11 | 2026-08-18 | 7 | $9K |
| BP2026-13873 | Improvement | Platinum Commercial | 2026-07-23 | 2026-08-17 | 25 | $330K |
| BP2026-13556 | Improvement | — | 2026-07-20 | 2026-08-06 | 17 | $3K |