How long does a Commercial / Multi Family Project permit take in Lincoln Park, Calgary?

Rolling 24 months · Sample: 40
Median days · Applied → Issued
29 days
Sample: 40 permits, last 24 months
Median days · Issued → Completed
130 days
From permit issuance to completion
City-wide median
42 days
Lincoln Park is 13 days faster

Recent examples in Lincoln Park

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-05282Improvement2026-04-062026-08-31147$443K
BP2026-12386ImprovementBhs Construction2026-07-032026-08-0634$480K
BP2026-13812Unspecified2026-07-232026-07-241$8K
BP2026-09099ImprovementPronafco Restoration2026-05-242026-07-0239$294K
BP2026-06430ImprovementBuild 3602026-04-212026-05-2231$60K