How long does a Commercial / Multi Family Project permit take in Lincoln Park, Calgary?
Median days · Applied → Issued
29 days
Sample: 40 permits, last 24 months
Median days · Issued → Completed
130 days
From permit issuance to completion
City-wide median
42 days
Lincoln Park is 13 days faster
Recent examples in Lincoln Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-05282 | Improvement | — | 2026-04-06 | 2026-08-31 | 147 | $443K |
| BP2026-12386 | Improvement | Bhs Construction | 2026-07-03 | 2026-08-06 | 34 | $480K |
| BP2026-13812 | Unspecified | — | 2026-07-23 | 2026-07-24 | 1 | $8K |
| BP2026-09099 | Improvement | Pronafco Restoration | 2026-05-24 | 2026-07-02 | 39 | $294K |
| BP2026-06430 | Improvement | Build 360 | 2026-04-21 | 2026-05-22 | 31 | $60K |