How long does a Single Construction Permit permit take in Lewisburg, Calgary?
Median days · Applied → Issued
17 days
Sample: 307 permits, last 24 months
Median days · Issued → Completed
183 days
From permit issuance to completion
City-wide median
18 days
Lewisburg is 1 days faster
Recent examples in Lewisburg
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15383 | New | Genesis Builders | 2026-08-13 | 2026-09-11 | 29 | $229K |
| BP2026-15176 | New | Homes by Avi | 2026-08-11 | 2026-09-09 | 29 | $242K |
| BP2026-12131 | New | Prominent Homes | 2026-06-30 | 2026-08-25 | 56 | $348K |
| BP2026-15209 | New | Prominent Homes | 2026-08-11 | 2026-08-24 | 13 | $360K |
| BP2026-12904 | New | Cardel Homes | 2026-07-10 | 2026-08-14 | 35 | $352K |