How long does a Residential Improvement Project permit take in Lakeview, Calgary?

Rolling 24 months · Sample: 94
Median days · Applied → Issued
19 days
Sample: 94 permits, last 24 months
Median days · Issued → Completed
123 days
From permit issuance to completion
City-wide median
17 days
Lakeview is 2 days slower

Recent examples in Lakeview

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14357NewGarage Suites2026-07-292026-09-0942$135K
BP2026-15379ImprovementBig Al S Texturing2026-08-132026-09-0927$40K
BP2026-15166ImprovementI Know a Guy Contracting Services2026-08-112026-09-0222$415K
BP2026-05515New2026-04-082026-08-31145$43K
BP2026-13722Improvement2026-07-222026-08-2534$782K