How long does a Commercial / Multi Family Project permit take in Keystone Hills, Calgary?

Rolling 24 months · Sample: 11
Median days · Applied → Issued
32 days
Sample: 11 permits, last 24 months
Median days · Issued → Completed
154 days
From permit issuance to completion
City-wide median
42 days
Keystone Hills is 10 days faster

Recent examples in Keystone Hills

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15213NewPartners Development Group Residential2026-08-112026-08-2817$654K
BP2026-12810NewPartners Development Group Residential2026-07-092026-07-2819$567K
BP2026-10562NewPartners Development Group Residential2026-06-102026-07-0929$568K
BP2026-05119NewPartners Development Group Residential2026-04-012026-05-0130$561K
BP2026-01416NewPartners Development Group Residential2026-01-302026-04-0767$561K