How long does a Commercial / Multi Family Project permit take in Keystone Hills, Calgary?
Median days · Applied → Issued
32 days
Sample: 11 permits, last 24 months
Median days · Issued → Completed
154 days
From permit issuance to completion
City-wide median
42 days
Keystone Hills is 10 days faster
Recent examples in Keystone Hills
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15213 | New | Partners Development Group Residential | 2026-08-11 | 2026-08-28 | 17 | $654K |
| BP2026-12810 | New | Partners Development Group Residential | 2026-07-09 | 2026-07-28 | 19 | $567K |
| BP2026-10562 | New | Partners Development Group Residential | 2026-06-10 | 2026-07-09 | 29 | $568K |
| BP2026-05119 | New | Partners Development Group Residential | 2026-04-01 | 2026-05-01 | 30 | $561K |
| BP2026-01416 | New | Partners Development Group Residential | 2026-01-30 | 2026-04-07 | 67 | $561K |