How long does a Single Construction Permit permit take in Huxley, Calgary?

Rolling 24 months · Sample: 334
Median days · Applied → Issued
15 days
Sample: 334 permits, last 24 months
Median days · Issued → Completed
202 days
From permit issuance to completion
City-wide median
18 days
Huxley is 3 days faster

Recent examples in Huxley

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16592NewTruman Homes2026-08-312026-09-1111$174K
BP2026-16593NewTruman Homes2026-08-312026-09-1111$174K
BP2026-15321NewShane Homes2026-08-132026-09-0927$271K
BP2026-15428NewSterling Homes2026-08-142026-09-0926$380K
BP2026-15038NewMorrison Homes2026-08-102026-09-0829$271K

Other permit types in Huxley