How long does a Commercial / Multi Family Project permit take in Horizon, Calgary?
Median days · Applied → Issued
55 days
Sample: 79 permits, last 24 months
Median days · Issued → Completed
113 days
From permit issuance to completion
City-wide median
42 days
Horizon is 13 days slower
Recent examples in Horizon
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16468 | Unspecified | — | 2026-08-28 | 2026-08-31 | 3 | $13K |
| BP2026-14847 | Unspecified | — | 2026-08-06 | 2026-08-24 | 18 | $5K |
| BP2026-06694 | Improvement | — | 2026-04-23 | 2026-08-18 | 117 | $35K |
| BP2026-09569 | Improvement | — | 2026-05-29 | 2026-08-04 | 67 | $50K |
| BP2026-12447 | Improvement | — | 2026-07-06 | 2026-07-31 | 25 | $251K |