How long does a Single Construction Permit permit take in Homestead, Calgary?
Median days · Applied → Issued
15 days
Sample: 388 permits, last 24 months
Median days · Issued → Completed
169 days
From permit issuance to completion
City-wide median
18 days
Homestead is 3 days faster
Recent examples in Homestead
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15126 | New | Partners Development Group | 2026-08-10 | 2026-08-27 | 17 | $184K |
| BP2026-15125 | New | Partners Development Group | 2026-08-10 | 2026-08-27 | 17 | $183K |
| BP2026-14871 | New | Partners Development Group | 2026-08-06 | 2026-08-27 | 21 | $184K |
| BP2026-14870 | New | Partners Development Group | 2026-08-06 | 2026-08-27 | 21 | $183K |
| BP2026-14132 | New | Trico Homes | 2026-07-27 | 2026-08-26 | 30 | $349K |