How long does a Single Construction Permit permit take in Homestead, Calgary?

Rolling 24 months · Sample: 388
Median days · Applied → Issued
15 days
Sample: 388 permits, last 24 months
Median days · Issued → Completed
169 days
From permit issuance to completion
City-wide median
18 days
Homestead is 3 days faster

Recent examples in Homestead

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15126NewPartners Development Group2026-08-102026-08-2717$184K
BP2026-15125NewPartners Development Group2026-08-102026-08-2717$183K
BP2026-14871NewPartners Development Group2026-08-062026-08-2721$184K
BP2026-14870NewPartners Development Group2026-08-062026-08-2721$183K
BP2026-14132NewTrico Homes2026-07-272026-08-2630$349K