How long does a Commercial / Multi Family Project permit take in Hamptons, Calgary?

Rolling 24 months · Sample: 3
Median days · Applied → Issued
5 days
Sample: 3 permits, last 24 months
Median days · Issued → Completed
91 days
From permit issuance to completion
City-wide median
42 days
Hamptons is 37 days faster

Recent examples in Hamptons

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-02906Improvement2026-02-262026-06-0397$3.9M
BP2025-21381Unspecified2025-11-032025-11-063$30K
BP2025-17112Unspecified2025-09-032025-09-085$3K