How long does a Commercial / Multi Family Project permit take in Greenview Industrial Park, Calgary?

Rolling 24 months · Sample: 55
Median days · Applied → Issued
77 days
Sample: 55 permits, last 24 months
Median days · Issued → Completed
86 days
From permit issuance to completion
City-wide median
42 days
Greenview Industrial Park is 35 days slower

Recent examples in Greenview Industrial Park

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-02764ImprovementCam Industrial Supply2026-02-242026-09-03191$193K
BP2026-05715ImprovementGraham Construction and Engineering2026-04-102026-08-12124$62.2M
BP2026-13619Improvement2026-07-212026-08-1121$0
BP2026-13217Unspecified2026-07-152026-07-2813$15K
BP2026-09463Improvement2026-05-282026-07-2255$70K