How long does a Commercial / Multi Family Project permit take in Great Plains, Calgary?
Median days · Applied → Issued
35 days
Sample: 43 permits, last 24 months
Median days · Issued → Completed
102 days
From permit issuance to completion
City-wide median
42 days
Great Plains is 7 days faster
Recent examples in Great Plains
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-05000 | Improvement | — | 2026-03-30 | 2026-09-09 | 163 | $0 |
| BP2025-04049 | Improvement | — | 2025-03-10 | 2026-09-01 | 540 | $4.3M |
| BP2026-06448 | Improvement | — | 2026-04-21 | 2026-07-31 | 101 | $507 |
| BP2026-11224 | Improvement | — | 2026-06-18 | 2026-07-15 | 27 | $250K |
| BP2026-02636 | Improvement | — | 2026-02-23 | 2026-03-31 | 36 | $303K |