How long does a Commercial / Multi Family Project permit take in Golden Triangle, Calgary?

Rolling 24 months · Sample: 8
Median days · Applied → Issued
109 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
41 days
From permit issuance to completion
City-wide median
42 days
Golden Triangle is 67 days slower

Recent examples in Golden Triangle

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-05543Improvement2026-04-082026-08-14128$2K
BP2026-08511ImprovementH2p Projects2026-05-152026-06-2238$95K
BP2026-02153Improvement2026-02-122026-06-01109$1K
BP2025-21813ImprovementGator Builds2025-11-102026-05-19190$375K
BP2025-17610ImprovementH2p Projects2025-09-092025-10-2041$160K