How long does a Commercial / Multi Family Project permit take in Garrison Woods, Calgary?

Rolling 24 months · Sample: 8
Median days · Applied → Issued
32 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
261 days
From permit issuance to completion
City-wide median
42 days
Garrison Woods is 10 days faster

Recent examples in Garrison Woods

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-10275NewGold Homes2026-06-052026-09-0289$809K
BP2026-14325Improvement2026-07-292026-08-2628$18K
BP2026-08209Unspecified2026-05-122026-07-0857$50K
BP2025-16594ImprovementAndm Industries2025-08-252025-09-1723$50K
BP2025-05939Improvement2025-04-042025-06-0562$200K