How long does a Commercial / Multi Family Project permit take in Garrison Woods, Calgary?
Median days · Applied → Issued
32 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
261 days
From permit issuance to completion
City-wide median
42 days
Garrison Woods is 10 days faster
Recent examples in Garrison Woods
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10275 | New | Gold Homes | 2026-06-05 | 2026-09-02 | 89 | $809K |
| BP2026-14325 | Improvement | — | 2026-07-29 | 2026-08-26 | 28 | $18K |
| BP2026-08209 | Unspecified | — | 2026-05-12 | 2026-07-08 | 57 | $50K |
| BP2025-16594 | Improvement | Andm Industries | 2025-08-25 | 2025-09-17 | 23 | $50K |
| BP2025-05939 | Improvement | — | 2025-04-04 | 2025-06-05 | 62 | $200K |