How long does a Commercial / Multi Family Project permit take in Franklin, Calgary?
Median days · Applied → Issued
41 days
Sample: 56 permits, last 24 months
Median days · Issued → Completed
97 days
From permit issuance to completion
City-wide median
42 days
Franklin is 1 days faster
Recent examples in Franklin
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10890 | Improvement | — | 2026-06-15 | 2026-09-11 | 88 | $40K |
| BP2026-15621 | Improvement | Royal Construction | 2026-08-17 | 2026-09-08 | 22 | $500K |
| BP2026-16015 | Unspecified | — | 2026-08-24 | 2026-09-03 | 10 | $4K |
| BP2026-12222 | Improvement | Cel Electrical Contractors | 2026-07-01 | 2026-07-28 | 27 | $75K |
| BP2026-09176 | Improvement | — | 2026-05-25 | 2026-07-16 | 52 | $120K |