How long does a Commercial / Multi Family Project permit take in Forest Lawn Industrial, Calgary?

Rolling 24 months · Sample: 22
Median days · Applied → Issued
54 days
Sample: 22 permits, last 24 months
Median days · Issued → Completed
129 days
From permit issuance to completion
City-wide median
42 days
Forest Lawn Industrial is 12 days slower

Recent examples in Forest Lawn Industrial

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-09714Unspecified2026-06-012026-06-032$4K
BP2026-00345New2026-01-092026-05-11122$1.2M
BP2026-05074Improvement2026-03-312026-04-2828$200K
BP2026-04785Improvement2026-03-262026-04-2732$20K
BP2026-03169Improvement2026-03-022026-04-2251$25K