How long does a Commercial / Multi Family Project permit take in Forest Lawn Industrial, Calgary?
Median days · Applied → Issued
54 days
Sample: 22 permits, last 24 months
Median days · Issued → Completed
129 days
From permit issuance to completion
City-wide median
42 days
Forest Lawn Industrial is 12 days slower
Recent examples in Forest Lawn Industrial
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-09714 | Unspecified | — | 2026-06-01 | 2026-06-03 | 2 | $4K |
| BP2026-00345 | New | — | 2026-01-09 | 2026-05-11 | 122 | $1.2M |
| BP2026-05074 | Improvement | — | 2026-03-31 | 2026-04-28 | 28 | $200K |
| BP2026-04785 | Improvement | — | 2026-03-26 | 2026-04-27 | 32 | $20K |
| BP2026-03169 | Improvement | — | 2026-03-02 | 2026-04-22 | 51 | $25K |