How long does a Commercial / Multi Family Project permit take in Forest Heights, Calgary?
Median days · Applied → Issued
34 days
Sample: 13 permits, last 24 months
Median days · Issued → Completed
98 days
From permit issuance to completion
City-wide median
42 days
Forest Heights is 8 days faster
Recent examples in Forest Heights
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11740 | Improvement | Norman Homes | 2026-06-25 | 2026-08-13 | 49 | $10K |
| BP2026-05896 | Improvement | — | 2026-04-14 | 2026-08-07 | 115 | $2K |
| BP2026-10003 | Unspecified | — | 2026-06-03 | 2026-06-06 | 3 | $5K |
| BP2026-07224 | Improvement | — | 2026-04-30 | 2026-06-03 | 34 | $60K |
| BP2026-02114 | Improvement | — | 2026-02-11 | 2026-04-15 | 63 | $4M |