How long does a Commercial / Multi Family Project permit take in Falconridge, Calgary?
Median days · Applied → Issued
49 days
Sample: 9 permits, last 24 months
Median days · Issued → Completed
140 days
From permit issuance to completion
City-wide median
42 days
Falconridge is 7 days slower
Recent examples in Falconridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2025-19699 | New | Kamex Construction | 2025-10-07 | 2025-12-16 | 70 | $118K |
| BP2025-19136 | Improvement | Rocky Cross Construction North Dba Dki Calgary | 2025-09-29 | 2025-11-03 | 35 | $50K |
| BP2025-19571 | Improvement | First Class Fencing | 2025-10-06 | 2025-10-09 | 3 | $15K |
| BP2025-13477 | Improvement | — | 2025-07-11 | 2025-08-29 | 49 | $20K |
| BP2025-11774 | Improvement | — | 2025-06-18 | 2025-07-29 | 41 | $20K |