How long does a Commercial / Multi Family Project permit take in Fairview Industrial, Calgary?
Median days · Applied → Issued
48 days
Sample: 57 permits, last 24 months
Median days · Issued → Completed
78 days
From permit issuance to completion
City-wide median
42 days
Fairview Industrial is 6 days slower
Recent examples in Fairview Industrial
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11084 | Improvement | Red Dot Restoration | 2026-06-17 | 2026-09-03 | 78 | $52K |
| BP2026-09796 | Improvement | Alberta Booth | 2026-06-01 | 2026-07-23 | 52 | $126K |
| BP2026-10290 | Improvement | — | 2026-06-06 | 2026-07-06 | 30 | $50K |
| BP2026-09753 | Improvement | Sorora Construction | 2026-06-01 | 2026-06-30 | 29 | $195K |
| BP2026-02931 | Improvement | Abc Consulting and Project Management | 2026-02-26 | 2026-06-12 | 106 | $135K |