How long does a Commercial / Multi Family Project permit take in Fairview Industrial, Calgary?

Rolling 24 months · Sample: 57
Median days · Applied → Issued
48 days
Sample: 57 permits, last 24 months
Median days · Issued → Completed
78 days
From permit issuance to completion
City-wide median
42 days
Fairview Industrial is 6 days slower

Recent examples in Fairview Industrial

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-11084ImprovementRed Dot Restoration2026-06-172026-09-0378$52K
BP2026-09796ImprovementAlberta Booth2026-06-012026-07-2352$126K
BP2026-10290Improvement2026-06-062026-07-0630$50K
BP2026-09753ImprovementSorora Construction2026-06-012026-06-3029$195K
BP2026-02931ImprovementAbc Consulting and Project Management2026-02-262026-06-12106$135K