How long does a Commercial / Multi Family Project permit take in Edgemont, Calgary?
Median days · Applied → Issued
42 days
Sample: 16 permits, last 24 months
Median days · Issued → Completed
136 days
From permit issuance to completion
City-wide median
42 days
Same as Edgemont
Recent examples in Edgemont
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-06377 | Improvement | Tayo Construction | 2026-04-20 | 2026-05-13 | 23 | $150K |
| BP2025-24075 | Unspecified | — | 2025-12-22 | 2026-04-27 | 126 | $80K |
| BP2026-00241 | New | Traugott Building Contractors | 2026-01-07 | 2026-04-07 | 90 | $3M |
| BP2025-19501 | New | Kamex Construction | 2025-10-03 | 2025-11-26 | 54 | $150K |
| BP2025-20970 | Improvement | — | 2025-10-27 | 2025-11-05 | 9 | $52K |