How long does a Commercial / Multi Family Project permit take in Edgemont, Calgary?

Rolling 24 months · Sample: 16
Median days · Applied → Issued
42 days
Sample: 16 permits, last 24 months
Median days · Issued → Completed
136 days
From permit issuance to completion
City-wide median
42 days
Same as Edgemont

Recent examples in Edgemont

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-06377ImprovementTayo Construction2026-04-202026-05-1323$150K
BP2025-24075Unspecified2025-12-222026-04-27126$80K
BP2026-00241NewTraugott Building Contractors2026-01-072026-04-0790$3M
BP2025-19501NewKamex Construction2025-10-032025-11-2654$150K
BP2025-20970Improvement2025-10-272025-11-059$52K

Other permit types in Edgemont