How long does a Commercial / Multi Family Project permit take in Eastfield, Calgary?
Median days · Applied → Issued
34 days
Sample: 15 permits, last 24 months
Median days · Issued → Completed
44 days
From permit issuance to completion
City-wide median
42 days
Eastfield is 8 days faster
Recent examples in Eastfield
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14183 | Improvement | Cam Industrial Supply | 2026-07-28 | 2026-08-22 | 25 | $14K |
| BP2026-15246 | Unspecified | Sprouse Fire and Safety | 2026-08-12 | 2026-08-19 | 7 | $5K |
| BP2026-04093 | Improvement | — | 2026-03-17 | 2026-08-05 | 141 | $90K |
| BP2025-10843 | Improvement | — | 2025-06-06 | 2026-07-07 | 396 | $0 |
| BP2026-01413 | Improvement | Facility Maintenance | 2026-01-30 | 2026-04-23 | 83 | $717K |