How long does a Commercial / Multi Family Project permit take in East Fairview Industrial, Calgary?
Median days · Applied → Issued
28 days
Sample: 40 permits, last 24 months
Median days · Issued → Completed
105 days
From permit issuance to completion
City-wide median
42 days
East Fairview Industrial is 14 days faster
Recent examples in East Fairview Industrial
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16554 | Unspecified | — | 2026-08-31 | 2026-09-03 | 3 | $3K |
| BP2026-15172 | Unspecified | — | 2026-08-11 | 2026-08-19 | 8 | $0 |
| BP2026-03472 | New | Solar Yyc | 2026-03-06 | 2026-07-16 | 132 | $1.1M |
| BP2026-09454 | Improvement | Chandi Construction | 2026-05-28 | 2026-07-02 | 35 | $1.2M |
| BP2026-05221 | Improvement | Traugott Building Contractors | 2026-04-03 | 2026-06-08 | 66 | $861K |