How long does a Commercial / Multi Family Project permit take in East Fairview Industrial, Calgary?

Rolling 24 months · Sample: 40
Median days · Applied → Issued
28 days
Sample: 40 permits, last 24 months
Median days · Issued → Completed
105 days
From permit issuance to completion
City-wide median
42 days
East Fairview Industrial is 14 days faster

Recent examples in East Fairview Industrial

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16554Unspecified2026-08-312026-09-033$3K
BP2026-15172Unspecified2026-08-112026-08-198$0
BP2026-03472NewSolar Yyc2026-03-062026-07-16132$1.1M
BP2026-09454ImprovementChandi Construction2026-05-282026-07-0235$1.2M
BP2026-05221ImprovementTraugott Building Contractors2026-04-032026-06-0866$861K