How long does a Commercial / Multi Family Project permit take in Dover, Calgary?
Median days · Applied → Issued
47 days
Sample: 19 permits, last 24 months
Median days · Issued → Completed
173 days
From permit issuance to completion
City-wide median
42 days
Dover is 5 days slower
Recent examples in Dover
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12894 | Improvement | — | 2026-07-10 | 2026-08-17 | 38 | $40K |
| BP2026-11731 | Improvement | Vision General Contracting | 2026-06-25 | 2026-07-17 | 22 | $75K |
| BP2026-11768 | Unspecified | — | 2026-06-25 | 2026-07-10 | 15 | $15K |
| BP2026-08965 | Unspecified | — | 2026-05-22 | 2026-05-29 | 7 | $8K |
| BP2026-04753 | Improvement | Maxim Building Restoration | 2026-03-26 | 2026-04-13 | 18 | $46K |