How long does a Commercial / Multi Family Project permit take in Douglasdale/Glen, Calgary?
Median days · Applied → Issued
29 days
Sample: 64 permits, last 24 months
Median days · Issued → Completed
145 days
From permit issuance to completion
City-wide median
42 days
Douglasdale/Glen is 13 days faster
Recent examples in Douglasdale/Glen
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15088 | Improvement | Amelco Electric Calgary | 2026-08-10 | 2026-08-24 | 14 | $15K |
| BP2026-10400 | Improvement | — | 2026-06-08 | 2026-08-18 | 71 | $450K |
| BP2026-12563 | Improvement | Remington Development | 2026-07-07 | 2026-08-10 | 34 | $91K |
| BP2026-13253 | Improvement | — | 2026-07-15 | 2026-08-07 | 23 | $800K |
| BP2026-12785 | Improvement | Labbe Leech Interiors | 2026-07-09 | 2026-08-01 | 23 | $200K |