How long does a Residential Improvement Project permit take in Diamond Cove, Calgary?
Median days · Applied → Issued
14 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
32 days
From permit issuance to completion
City-wide median
17 days
Diamond Cove is 3 days faster
Recent examples in Diamond Cove
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-06630 | Improvement | True North Concrete Cutting and Coring | 2026-04-23 | 2026-05-05 | 12 | $8K |
| BP2025-18912 | Improvement | — | 2025-09-25 | 2025-10-28 | 33 | $2K |
| BP2025-14747 | Improvement | True North Concrete Cutting and Coring | 2025-07-29 | 2025-08-06 | 8 | $4K |
| BP2025-12803 | New | — | 2025-07-02 | 2025-07-18 | 16 | $3K |
| BP2024-24771 | Improvement | — | 2024-11-26 | 2024-12-03 | 7 | $0 |