How long does a Commercial / Multi Family Project permit take in Deerfoot Business Centre, Calgary?

Rolling 24 months · Sample: 45
Median days · Applied → Issued
35 days
Sample: 45 permits, last 24 months
Median days · Issued → Completed
76 days
From permit issuance to completion
City-wide median
42 days
Deerfoot Business Centre is 7 days faster

Recent examples in Deerfoot Business Centre

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-09370ImprovementGovan Brown & Associates2026-05-272026-08-0772$5M
BP2026-05110NewPCL Construction2026-04-012026-07-10100$20.9M
BP2026-11600ImprovementGovan Brown & Associates2026-06-232026-07-0310$10K
BP2026-08935Unspecified2026-05-212026-05-298$6K
BP2025-23176Improvement2025-12-042026-05-13160$255K